Kearney provided the design, installations, switchovers, and commissioning for the electrical service entrance sections for 13 buildings on the Tempe Campus.

Completion:
01-04-2011

Method:
GMP

Owner:
Arizona State University

Size:
13 Buildings

Complexity:
Electrical Renovation

Contractor:
Big D Construction

Unique Aspects:

  • Very careful planning was needed which ensured no disruptions to campus operations.
  • Original buildings were built around old systems making gear removal very difficult.
  • Old systems did not provide grounding, so GFIs were added.
  • Power was reestablished 10-12 hours ahead of time on each phase of the upgrade.

Services Provided:

  • Pre-construction Design
  • Electrical Renovation
  • Electrical Commissioning